Phase 3: Car Park down ramp approach
- NOE CE25-66397 – 21 July to 25 July 2025
- Bus lane closed past this location
Phase 4: Tour stands MT – between Grosvenor and Brooke gates
- NOE CE25-66398A – 24 July to 16 August 2025
- Tour stands closed (no alternative can be provided)
- Bus lane closed past this location
- Bus stand GH remains open for authorised operators only
Phase 5 & 6: Speaker’s Corner stops W (Bus), 14 (Coach) & Z (Tour)
- 5: NOE CE25-66400A – 19 August to 30 August 2025
- 6: NOE CE25-66402A – 1 September to 18 September 2025
- Stops are closed in two phases of works (approximate dates as above) with half the stop space remaining open
- Scheduled coaches: Should not serve these stops between 08:00 to 20:00 daily– alternative stops depending on line of route: Bayswater Road stop A or Portman Street stop M.
- Tour buses: Can continue to serve the open stops in each phase but must keep dwell times to an absolute minimum
- Bus lane closed past this location, two traffic lanes remain open
After the works detailed above some overnight closures are likely to be required for other works, but these are TBC.
(taken from the TfL website)