We now have updated dates for the Park Lane works, in addition to bus NOEs (attached), from Monday 19 May until Thursday 18 September. All dates continue to be subject to change.
These works are to make permanent the infrastructure that was put in place for the Park Lane cycle lane. The works will be undertaken in six phases working south to north in localised worksites along the northbound carriageway using lane restrictions. Where the bus lane is closed it is only in the immediate vicinity of the worksite. Planned events, such as concerts, have been taken into account during the works planning.
Phase 1A & 1 B: Bus stop Y and Tour stop X – Achillies Way
- 1A: NOE CE25-66834 – 19 May to 19 June 2025
- 1B: NOE CE25-66395 – 20 June to 30 June 2025
- Bus stop and tour stop will be partly closed in each phase. Due to capacity constraints tour buses should not serve either stop but can use stop T further north as an alternative.
- Bus lane closed past this location
Phase 2: Coach parking bays (x4) prior to Stanhope Gate
Works TBC
- 19 May to 29 May 2025 2 June to 12 June 2025
- Coach parking bays closed
- Bus lane open
Phase 5 & 6: Speaker’s Corner stops W (Bus), 14 (Coach) & Z (Tour)
- 5: NOE CE25-66400 – 19 August to 3 September 2025
- 6: NOE CE25-66402 – 3 September to 18 September 2025
- Stops are closed in two phases of works (approximate dates as above) with half the stop space remaining open
- Scheduled coaches: Should not serve these stops between 08:00 to 20:00 daily– alternative stops depending on line of route: Bayswater Road stop A or Portman Street stop M.
- Tour buses: Can continue to serve the open stops in each phase but must keep dwell times to an absolute minimum
- Bus lane closed past this location, two traffic lanes remain open
After the works detailed above some overnight closures are likely to be required for other works, but these are TBC.